University of Bath, Parade Bar

Key Facts

Value:
£475k
Sector:
Programme:
10 Weeks
Scope of work:
The fast-track design and fit out of this café and bar space including new commercial catering facilities, construction of a bespoke bar, flooring, ceilings and associated mechanical & electrical works.

This project was extremely time critical and was programmed to fit into the summer vacation period of 2011. Following asbestos removal we installed all new mechanical and electrical systems, cold rooms, bespoke bar and joinery, external soffits and cladding, new flooring and decorations throughout.

The project involved careful co-ordination of the services and building fabric elements of the work and a commitment to working out of hours to deliver a quality product that was fully operational for the start of the 2011 term. We have the ability to meet time critical projects and deliver a quality product to clients within strict client budgets.