Works to the new build Tiddlers Pre-School Nursery in Saltford are now complete and the facility was officially opened yesterday following a successful open day on Saturday. The 2600 sq ft nursery is based within the grounds of Saltford School and includes two classrooms, kitchen space, staff offices, WCs and apparatus storage.

The design involved extensive sub structures, block and beam flooring and a timber framed glulam structure with single ply roof and faceted elevations. In order to access the site, substantial temporary roads and hardstandings were formed and B&S Site Manager Steve Dimery focused on Site Health and Safety to ensure the wellbeing of all Saltford Primary School pupils, staff and visitors during the 22 week build period. Project Case Study to follow shortly.

Works commence on the 6th August to a number of teaching areas across UWE's Bower Ashton Campus. This seven week scheme is a follow on from our 2011 Summer works and is being managed by Joe Payne, Lee Hardwell and Owen Beckett.